Friday, October 29, 2010

Brick columns complete

The brick finally arrived from South Carolina this week and the brick masons are about done. The 4 large columns at the north side are done and add a lot of character to the large wall.
Published with Blogger-droid v1.6.3

Tuesday, October 26, 2010

Drywall started

The drywall is being Hung in the new foyer. The installers hope to have the building almost complete by the end of the week.
Published with Blogger-droid v1.6.3

Thursday, October 21, 2010

concrete Aprons

The remaining mechanical pad sections have been poured as well as several sections of the concrete aprons. As soon as the remaining brick arrive and is laid, we will back fill and pour all of the sidewalks.
Published with Blogger-droid v1.5.9

Friday, October 15, 2010

Gutters and fascia

The metal is going up around the building. Much of the fascia is up, and today several sections of gutters and downpour were installed.
Published with Blogger-droid v1.5.9

Thursday, October 14, 2010

Insulation going in

Insulation started going in the building yesterday evening. A good portion of the chapel ceiling is done, as well as many of the exterior walls.
Published with Blogger-droid v1.5.9

Tuesday, October 12, 2010

Brick arches over the windows

Brick has been laid around the east side of the building. The only part that is left now is a little at the north and the main entry on the east side.
Published with Blogger-droid v1.5.9

Wednesday, October 6, 2010

Brick on the east side of the building

The masons have started brick on the east side of the building.
Published with Blogger-droid v1.5.9

Monday, October 4, 2010

The brick work is almost halfway complete

the brick masons have completed all of the brick work on the east side of the building. Only a little bit on the northside and all of the west side remain.
Published with Blogger-droid v1.5.9

Finishing framing items

the framer spent most of the day adding the remaining ceilings and plywood to shear walls. They also added the missing catwalk and moved several closet doors in the cultural center.
Published with Blogger-droid v1.5.9

Friday, October 1, 2010

Brick by brick

With a crew of 6 brick masons, there is more progress being made. They plan to work Saturday and finish the columns at the entry.
Published with Blogger-droid v1.5.9